Monday, 23 April 2007

TSP Documents

The following are in chronological order:-
--Siemens had submitted the Turbo-Supervisory Panel drawings (Rev. 0) on 7th Dec.
--DCPL comments on the drawings on 15th Dec. with action 4
--Siemens replies to DCPL's comments. (Moral of their replies is 'Siemens is correct and nothing will change in the drawings).
--DCPL responds to their replies and conveys that the same is agreed. (please refer email dated 15th Feb 'Re:Solaris - Doc Approval')
--Since, there will be no change in the TSP documents, Siemens doesn't forward any revised drawings.
--On the 23rd April, TSP documents were decided to be approved. But since, DCPL were left with no unstamped copies, Siemens was requested to issue fresh set of TSP documents, for us to stamp it Approved. Accordingly, an email was sent to Siemens.
--An email informed that Mr. Tathagata is out of office till 5th May.


UPDATE: It should be noted that, the same was informed once more to Siemens, through the email which reflected the Drive Control Philosophy (forwarded to both CVPL & Siemens / meeting with DCPL & Solaris on 18th Jan)

No comments: