During the process of creating the 'Pending Issues of Instrumentation' for the meeting held on 20th April, it was found out that Hyquip had not yet provided any C&I details relating to the CHP area till now. So, Mr. AKB suggested the C&I dept., to send an email to Hyquip, asking for the list of documents expected from their side. (Although, Mr. R.N.Das had already sent an email on 20th Oct. for some details of the CHP plant.)
Update: Mr. AKB enquires /doubts whether the 'list of documents' expected from Hyquip has to be so lengthy. It was confirmed that the list is accurate, since it was checked by MSPD. In fact, the chronology of the documents was set by himself.